Weiheng Engineering • Version 1.1 • November 2, 2026
Shared Test Platform and Fixture Changeover Worksheet
Project and configuration identity
| Project / platform | Configuration revision | Date | |||
|---|---|---|---|---|---|
| DUT variants / axes | Fixture / adapter IDs | Recipe IDs | |||
| Prepared by | Reviewed by | Release status |
Share or separate decision
| Decision dimension | Shared boundary to verify | Separate / redesign trigger | Project entry and evidence |
|---|---|---|---|
| Capacity and duty | Torque, speed, power, inertia, travel, thermal state, duration, direction, quadrant, and utilities | Different loading technology, safety class, or sustained-energy boundary | |
| Mechanical interface | Mounting, adapter, coupling, alignment, stiffness, load path, guarding, access, and cable motion | Unverified compliance, runout, resonance, preload, or service exposure | |
| Measurement plane | Sensor location, range, reference plane, timing, calculations, tare, and uncertainty treatment | Materially different plane, range, reference, or measurement principle | |
| Control and safety | Protocols, modes, limits, feedback, brake, fail-safe states, guards, interlocks, and stop behavior | Incompatible behavior cannot be isolated in the released configuration | |
| Evidence and permissions | Recipe, channel map, raw data, report, access, release, override, export, and retention boundaries | Customer, project, IP, or approval boundaries cannot be separated | |
| Availability | Changeover, stabilization, verification, maintenance, recovery, calibration downtime, and retest | Sharing creates an unacceptable queue, interruption, or restoration exposure |
Variant capacity record
| DUT / axis / fixture | Included components and interfaces | Operating and duty boundary | Measurements and safety state | Fixture / recipe / evidence IDs |
|---|---|---|---|---|
Fixture-changeover release
| Release check | Required record | Status / exception / evidence |
|---|---|---|
| Identity and revision | DUT, fixture, adapter, coupling, fastener, drawing, controller, software, and recipe revisions | |
| Physical installation | Condition, locating features, installation sequence, fastener method, alignment, load path, and cable or hose routing | |
| Protection and interfaces | Guards, interlocks, limits, brake, emergency stop, utilities, protocols, and safe-state behavior | |
| Measurement configuration | Sensor ranges, channel map, reference planes, timing, zero, tare, reference, and verification checks | |
| Controlled proving sequence | Approved low-risk sequence, expected response, exceptions, and stop criteria before the full test envelope | |
| Release decision | Open items, authorization, effective configuration, permitted DUT and envelope, and required re-verification |
Scope limit: This worksheet defines a review and release structure. It makes no universal claim for Weiheng platform capacity, changeover time, accuracy, availability, customer results, or project acceptance. Project values require approved records.